NASA Unveils Revised Artemis 3 Plan With Three Rockets and Two Lander Tests

NASA has detailed a revised plan for Artemis 3, transforming what was once planned as a crewed lunar landing into a complex Earth-orbit test of two commercial lunar lander designs, with three spacecraft launching on three heavy rockets within about two weeks.

ताजे अपडेट पाने के लिये हमारे ग्रुप को ज्वाइन करें Join Now

The mission will begin with Blue Origin launching its New Glenn rocket, placing a test variant of the Blue Moon Mark 2 lander into low Earth orbit at about 440 kilometres. NASA will then launch its Space Launch System carrying the Orion capsule and a four-person crew, NASA astronauts Randy Bresnik, Frank Rubio and Andre Douglas alongside European Space Agency astronaut Luca Parmitano, into a 555-kilometre orbit. The crew will dock Orion with the Blue Moon lander and spend two days inside it testing environmental controls, life support and flight software.

After undocking, Orion will perform a second, shorter rendezvous with SpaceX’s Starship Version 3, lasting about two hours. The crew will not enter the Starship capsule, only verifying how Orion docks and undocks with it. NASA says the dual approach will demonstrate how Orion interfaces with two very different commercial lander architectures during a single mission, and will also test new Orion Crew Survival System suits.

No firm launch date has been set. A NASA memo reported last month acknowledged Artemis 3 is three months behind schedule, with a best-case launch in summer 2027, keeping two landing opportunities open for Artemis 4 in 2028. In updated contracts announced on October 27, SpaceX added two demonstrations of its Starship crew cabin and Blue Origin added human-in-the-loop testing and hardware readiness milestones, while a non-propulsive spacer replaces the interim cryogenic propulsion stage on the SLS.